National Grid has submitted its planning application for the Norwich–Tilbury project: 180 kilometres of high-voltage pylons stretching across Norfolk, Suffolk and Essex.
Local campaigners, including South Suffolk MP James Cartlidge, have opposed the plans for years.
“There are those who say those who oppose pylons must be NIMBYs,” says Cartlidge in a video posted on X. “On the contrary, I strongly support efforts to boost our energy security – we need offshore wind, just as we need North Sea oil and gas. But it has to be transmitted in a way that doesn’t permanently damage our countryside.”
Cartlidge argues that residents were only ever given one option – a line of pylons cutting through rural East Anglia – despite the existence of modern alternatives that could deliver the same result at comparable or even lower cost.
The search for alternatives
When National Grid first proposed the route, known then as East Anglia GREEN, as East Anglia Bylines reported at the time, alternatives such as offshore or underground transmission were dismissed as “impossible.”
Yet similar projects are already protecting the countryside elsewhere in Britain. From Scotland to Wales and the North of England, billions are being invested in offshore systems such as the Western Link and Eastern Green Link – and these have added only about £6.50 a year to consumer bills.
That inconsistency prompted Cartlidge’s campaign for “fair treatment” for East Anglia. The aim was not to block new electricity infrastructure but to ensure the public could see a fair cost comparison between pylons and other technologies.
Following pressure from MPs and local campaigners, the Electricity System Operator (ESO) – which has since transitioned into the new National Energy System Operator (NESO) – agreed to commission an independent study to assess alternative ways to move electricity from offshore wind farms off the East Anglian coast to where it’s needed inland.
What the East Anglia study found
Published in March 2024, NESO’s East Anglia Study compared the proposed pylon route with an alternative using underground high-voltage direct-current (HVDC) cables.
The study’s conclusion was striking: assuming both options were measured against the same completion baseline of 2034, underground HVDC could be delivered at comparable or even lower cost than pylons. It also found that HVDC’s greater efficiency would reduce “constraint payments” – the costly compensation paid to electricity generators when the grid cannot transmit power due to physical limitations.
The findings were repeatedly tested and confirmed by ESO’s senior engineers.
What is HVDC and why does it matter?
High-Voltage Direct Current (HVDC) is a modern technology that transmits electricity more efficiently over long distances than the traditional High-Voltage Alternating Current (HVAC) system used by most pylons.
- Lower energy loss: HVDC lines lose less power during transmission.
- Better for long distances: They can run underground or under the sea, making them ideal for connecting offshore wind farms.
- Used abroad: In Germany, underground HVDC is now the legal default for new transmission projects.
While installing underground cables is disruptive during construction, the land is restored afterwards – unlike pylons, which leave a permanent mark on the landscape. As Cartlidge notes:
“There’s a large water pipe being built through villages such as Raydon, and I’ve not had one single email complaining about it, because people know the land will be made good once the works are finished. Pylons, on the other hand, have lasting visual impact on our beautiful countryside.”
A fair comparison
Critics of the study have claimed underground HVDC only looks cheaper because the 2034 baseline gives pylons no “head start.” But Cartlidge argues that this is the only fair way to compare the two options.
“If you compare two sprinters, you make them start at the same time – you don’t give one a head start. Because National Grid refused to consider alternatives to pylons from the outset, the pylon option has effectively been given years of advantage.”
This argument highlights one of the campaign’s core frustrations: that East Anglia was not offered the same level of consideration as other regions where offshore or underground routes were chosen to protect local communities and landscapes.
What happens next?
National Grid and the Government have so far continued to back the Norwich–Tilbury pylon route, which is now with the Planning Inspectorate. Cartlidge hopes that the evidence from the East Anglia Study – showing a credible, cost-comparable alternative – will force a rethink.

“I will continue doing all I can to stand up for my constituents and push National Grid and the Government to look again at the alternatives. The evidence shows there are better, less damaging ways to deliver clean energy across East Anglia.”
Modern solutions for a modern grid?
The transformation of Britain’s energy system is essential to meeting climate targets and securing affordable power. But, as Cartlidge and others argue, it must also be done fairly.
The creation of NESO, a new public body responsible for planning the UK’s whole energy network – including electricity, gas and hydrogen – offers a chance to reset how infrastructure decisions are made.
East Anglia is already central to Britain’s renewable revolution, hosting some of the country’s most ambitious offshore projects. Cartlidge insists that should be matched by modern infrastructure that respects the region’s environment and communities:
“This isn’t about rejecting progress – it’s about demanding fairness, innovation and respect for the countryside at the heart of East Anglia’s identity.”
National Grid defends its plans and timeline
National Grid says delaying delivery until 2034 is around £1bn worse for consumers in all study cases, in part due to the cost of needing to pay wind operators to turn off the wind power over this period due to lack of capacity in the grid. This cost would be passed onto energy bill payers.
They also point out that that the HVDC solution would deliver only 4GW compared to the 6.9GW for the overhead power lines. “Our role is to find a way to take the home-grown, more affordable and cleaner energy from where it’s generated to where it’s needed,” explains a National Grid spokesperson. “We consider all technology options – offshore, underground, and overhead lines – and then balance a range of factors, including what’s possible from an engineering and environmental perspective. We also share our plans with Ofgem, our regulator, to ensure value for money for bill payers.”
Norwich–Tilbury project clears first hurdle as scrutiny begins
The Planning Inspectorate has accepted National Grid’s Norwich–Tilbury application, moving the project into the pre-examination phase. Over the next few months, local authorities, landowners and residents will be able to register as interested parties before the formal hearings begin.
For National Grid, it is a key milestone in its Great Grid Upgrade — a national push to connect cleaner, cheaper power to homes and businesses. For campaigners such as James Cartlidge, it is also a critical moment to prove that clean energy and countryside protection do not have to be in conflict.
As the examination gets underway, East Anglia finds itself at the heart of a national dilemma: how to deliver the infrastructure needed for a low-carbon future without losing the very landscapes that make that future worth building.
This article has been updated to accommodate a response from National Grid.