If we are to ever reach net zero, the UK needs to replace fossil fuels with a massive increase in sustainable electricity supply. We need it to drive heat pumps to heat homes and buildings; to power our cars, buses, trains and lorries; for energy intensive industries; and to feed the huge server farms which drive the internet and artificial intelligence. Although efficiency measures like home insulation, and local solar panels on roofs will help, they can only make a small contribution to a very large and growing demand.
Lots of power, but in the wrong place
Fortunately, we have the means to do this. We have a lot of wind, one of the highest tidal ranges in the world, and more sunshine than our folklore admits. At present, wind currently makes by far the largest contribution. Last year, nearly a third of the UK’s electricity supply came from wind.
However, while the shallow, but windy, North Sea is ideal for generating wind power, it is a long way from the urban locations where most of the power is used. In East Anglia (and off our coast), we currently generate 5.6 GW of electricity, but we never use more than 1.3 GW of it. Most of it is transferred to the rest of the country through the national grid. But because the national grid is old, and designed for a different world, we can’t always get access to the power which is available.
So work is in hand to upgrade the grid, most controversially by new pylon lines crossing Norfolk, Suffolk and Essex.
Managing the grid
Managing the grid is a complex balancing act. We need a constant reliable supply, but demand fluctuates from minute to minute, and wind and sunlight are not entirely predictable. So, the Electricity System Operator (ESO) which manages the flow, has to be able to constantly adjust – switching between sources when the wind drops, or exporting surplus to other countries when we are generating more than we need. The grid also needs spare capacity, in case a generator fails, or a cable is damaged.
But upgrading the grid is expensive and controversial. As always in planning, there is a tension between the national need and the people most directly affected. The nation may need more electricity, but none of us want a pylon line at the bottom of our garden. We have previously reported on the debates over plans for trenches across Norfolk and pylon lines across Suffolk and Essex, and the potential of offshore cables (an ‘offshore ring main’) to take power from the North Sea to connect to the grid in the Thames estuary.
The aim
The government’s net zero plans aim to almost triple electricity generation in East Anglia (or off its shores), taking us from the 5.6 GW which we generate now, to potentially 16.1 GW by 2030. Almost all of that electricity will need to be sent on to other parts of the country or to Europe, by cables under the sea, underground or over our heads.

None of this is simple. A major challenge is connecting 11 new windfarms to the grid by 2030, including the world’s largest offshore generator – the 2.9 GW Hornsea 3 windfarm. In an ideal world, these would have all been planned together, but that is not what has happened, and work is already advanced on several of them. Cables for six of these will come ashore in North Norfolk, and run underground to substations near Norwich and at Necton, near Swaffham. Three come ashore in Suffolk, feeding substations at Friston, near Aldeburgh, or a new one at Bramford near Ipswich. The routes for the remaining two are still to be agreed. Three new international interconnector cables will connect to the rest of Europe, enabling us to import or export electricity when necessary. The four substations will all need upgrading to handle the additional power. And all that power needs to get from these substations to the main grid around the Thames estuary.
Three transmission methods
There are three ways of transmitting the electricity. The most familiar is alternating current (AC) cables, carried on 50 metre tall overhead pylon lines. It is quick and cheap to install, and easy to repair and modify when needs change. The second is underground AC cables. This is much less obtrusive once laid, but more expensive, and it only works over relatively short distances (20 km). The third option is high voltage direct current (DC) cables, underground, or offshore. These are more efficient, and work over longer distances. However, they can carry less current, so more cables are required. They are more complex and therefore more prone to faults. They are more difficult to modify, and there are global shortages of the necessary materials.
The ESO’s role
The Electricity System Operator (ESO) is responsible for planning for future energy supply. It is independent of the power companies who sell the power, and of the National Grid, which provides the physical infrastructure to get the power from where it is generated to where it is used..
After widespread objections to the current plans, which involve long overhead pylon lines across Norfolk, Suffolk and Essex, ESO have now published an analysis of a series of alternative approaches. It has tested these against four design objectives:

No good answer
Balancing these four against each other is not easy. The estimated capital cost of the current plan is £2.7bn, and it is expected to deliver by the target date of 2030. The ESO study considered nine alternatives to that plan, four of which were proposed by local community groups. The report analyses each in detail and the table below summarises their conclusions. The cost columns show how much more expensive each option would be than that plan.

No option wins on all the four assessment criteria. Since only two could deliver by 2030, the final column considers what would happen if the delivery date was moved to 2034.
With that extension, underground DC cables, and hybrid underground/offshore DC cables are comparable with the current plan. However, there are serious issues about the deliverability of the HVDC options because of global shortages of materials. Option 8, which scores well on most criteria, is high risk because it involves a technical complexity not tried anywhere before. All options raise environmental issues, and there is room for debate about the weighting of the options. The mainly offshore options score well for community impact, but lowest on other criteria.
The missing ring main
There has been much campaigning for an ‘offshore ring main’ to connect all North Sea windfarms at sea. This would remove the need for new substations, pylon lines and trenching across East Anglia. This has been supported by the Offshore Electricity Grid Task Force of MPs.
In 2020, ESO published a report on this which argued that in the long term (to 2050), an offshore ring main could save £6bn. However, it also concluded that because the necessary technology was still evolving, this could not be completed to meet the government’s target dates. And major infrastructure work has now begun in Norfolk on the overland routes, including substation upgrading and cable laying for the Norfolk Hornsea 3 windfarm, and for the Vanguard and Boreas windfarms.
The present report appears to confirm those earlier conclusions, and did not consider this option, which was deemed to be outside the terms of reference.
What next?
This issue puts two ‘green’ issues at war with each other. The quickest and cheapest way of moving towards net zero is a solution which produces a blot on some outstanding rural landscapes.

There is no doubt that major change to the grid is necessary, to connect both the new offshore generators, and those onshore projects – wind turbines and solar farms – which are ready to build, but which currently have to wait years for a grid connection. The faster the change happens, the sooner we reach net zero. There are technical and supply chain uncertainties about the most socially acceptable options – underground and offshore, and the more expensive options inevitably involve higher costs to consumers in the end.
Many people will be understandably angry if the overhead options go ahead, but given the urgency of meeting the net zero targets, it seems very likely that this will be the outcome. In November, Rachel Reeves, the Shadow Chancellor confirmed that a Labour government would support the overhead cable options.
The battle is far from over though. The protest groups will no doubt be working on a response to the report, and there will debates about the detailed assessments in the summary table. There may well also be legal challenges and planning issues as things move forward.
As so often with major infrastructure projects, it would have been better to do this a decade ago, but we are where we are, and the need is urgent.